2 Post Lift

Not true about the 30 days. Cure the slab for a minimum of 7 days and then install the lift. Then wait another 3 weeks before using it to allow the slab to attain full design strength.

The actual weight of the lift equipment can easily be handled by the concrete after a 7 day cure.

I'm only offering this advice in case it will help any of you get your lift in.

just looked in my instructions......they say 28 days before installation. pretty close with a 30 day guess