Metal Building/ Garage…

Thanks man, I really appreciate it. That actually doesn't sound too bad all things considered. I guess as with anything else, it all nickle and dimes you in the end with the slab, building, electrical, and all the other details. I realize the slab was poured a while back, but any idea what that slab would run in today's dollars?

So I had that done a few years ago. At the time it was about 12,000 for everything. The loads of base rock, the rental for the compactors, all materials, rebar, forms etc etc and the concrete crew/finishers I hired. I rented a pump guy also, he was a grand. It was 38 yards, 4 trucks came out at the same time. It was stressful and it worked the guys pretty hard. They had to rush.

In todays time I’d bet it be 16-18k for that same monolithic slab.